Build Times

Quality not quantity, that's what we are about at Snug garden rooms.

We take great pride in our work and take the time to do things right, craftmanship takes a little longer.

Average Build Times

1. Load out materials

.5 Day

2. Foundations

1.5 Days

3. Wooden floor

1.5 Days

4. Build walls

1.5 Days

5 Days Total

5. Build roof

1 Day

6. Membrane/ battens

1 Day

7. Cladding

2 Days

8. Roof rubber & trim

1 Day

10 Days Total

9. Fit windows & doors

1 Day

10. Insulation/ foil

1.5 Days

11. Internal battens

.5 Day

12. Electrics (1st fix)

1 Day

14 Days Total

13. Plasterboard/ skim

2.5 Day

14. Fit MVHR

1 Day

15. Electrics (2nd fix)

1 Day

16. Guttering/ drainage

.5 Day

19 Days Total

17. Skirting & finishing touches

1 Day

18. Cleaning

1 Day

17. Skirting

.5 Day

18. Cleaning/ finishing

.5 Day

20 Days Total

Please note;  Adverse weather can add additional days to the average garden room build time.

Generally it is advised that our garden rooms will take around 3-6 weeks to build to a high standard depending on size, complexity and weather.

Made To Order, Built To Last

As a small, local company, we’re big on delivering high quality garden rooms and a friendly, personal service.

Request a Brochure

Our garden room brochure has been tailored for you. We’ve included everything you need to know about our beautiful garden rooms. You’ll also find examples of popular designs along with details of our premium upgrades. All for you to go through at your own, convenient time.