Average Build Times
1. Load out materials
.5 Day
2. Foundations
1.5 Days
3. Wooden floor
1.5 Days
4. Build walls
1.5 Days
5 Days Total
5. Build roof
1 Day
6. Membrane/ battens
1 Day
7. Cladding
2 Days
8. Roof rubber & trim
1 Day
10 Days Total
9. Fit windows & doors
1 Day
10. Insulation/ foil
1.5 Days
11. Internal battens
.5 Day
12. Electrics (1st fix)
1 Day
14 Days Total
13. Plasterboard/ skim
2.5 Day
14. Fit MVHR
1 Day
15. Electrics (2nd fix)
1 Day
16. Guttering/ drainage
.5 Day
19 Days Total
17. Skirting & finishing touches
1 Day
18. Cleaning
1 Day
17. Skirting
.5 Day
18. Cleaning/ finishing
.5 Day
20 Days Total
Please note; Adverse weather can add additional days to the average garden room build time.
Generally it is advised that our garden rooms will take around 3-6 weeks to build to a high standard depending on size, complexity and weather.
Made To Order, Built To Last
As a small, local company, we’re big on delivering high quality garden rooms and a friendly, personal service.
Request a Brochure
Our garden room brochure has been tailored for you. We’ve included everything you need to know about our beautiful garden rooms. You’ll also find examples of popular designs along with details of our premium upgrades. All for you to go through at your own, convenient time.
Home Visit
Brochure
Call Us
Message Us